Sovereign Square

Location 
Leeds

Main Contractor
GMI Construction

Project
£62.7m development of a 12-storey, 305-bedroom new Hyatt Hotel.

Contract

  • 1MVA substation
  • Water supply
  • Temporary builders’ supply

Delivery

  • Busy city centre location with 200m offsite route to point of connection
  • Worked closely with Leeds City Council on traffic management, keeping disrupti`on to a minimum
  • Energised ahead of schedule enable temporary supply to be removed early on in the build programme.