Location
Oldham
Main Contractor
Tilbury Douglas
Project
1,500 pupil secondary school.
Contract
- 800kVA HV/LV electrical supply
- 180mm gas mains connection
- 110mm water supply
Delivery
- Early-stage design and installation enabled as part of road construction
- Worked with single point of access to site
- Supported new bridge design, enabling access to point of connection
- Incorporated network provision for 70-plot housing development.