Location
Manchester
Main Contractor
Capital & Centric
Project
Iconic mixed use development in the heart of Manchester.
Contract
- Investigative disconnections prior to connection works
- Multi-utility infrastructure
- Three integrated substations with 3MVA load
- Offsite point of connection (POC)
Delivery
- Worked closely with M&E contractor to manage central location for incoming utilities, combined with phased distribution across the site
- Coordination with Council to manage
- HV cable lay to city centre POC.