Location
Whalley, Lancashire
Housebuilder
Prospect Homes
Project
50 plot new homes development on brownfield site
Contract
- Disconnection of 33 houses ahead of demolition works
- Diversion of electricity, gas and water mains
- Installation of multi-utilities for new 50-plot development
Delivery
- Our first new connections project for Prospect Homes
- We managed the disconnection and diversion works in line with the site clearance programme and remained as part of the team to see the new plots energised ready for new residents