Location
Manchester
Main Contractor
Renaker
Project
32-storey, 450 apartment, mixed-use high rise development as part of Manchester’s £740m Northern Quarter regeneration.
Contract
- 2 x 1MVA substations
- 2 x gas service provision
- Potable water and wastewater removal and drainage
Delivery
- 700m offsite route to point of connection in Piccadilly Gardens with city centre traffic management during Christmas Markets
- Electrical design rework and construction of a platform to contain HV cables and enable early testing
- Water supply connected and metered ahead of practical completion