Location
Leeds
Main Contractor
GMI Construction
Project
£62.7m development of a 12-storey, 305-bedroom new Hyatt Hotel.
Contract
- 1MVA substation
- Water supply
- Temporary builders’ supply
Delivery
- Busy city centre location with 200m offsite route to point of connection
- Worked closely with Leeds City Council on traffic management, keeping disrupti`on to a minimum
- Energised ahead of schedule enable temporary supply to be removed early on in the build programme.