Location
Staffordshire
Housebuilder
MCI Developments
Project
60 new homes energised for a Homes England project.
Contract
- Design and installation of substation to power 60 plots
- Delivery required in eight months after taking over contract from previous ICP.
Delivery
- Timelines achieved by re-engaging solicitors, assigning two site teams, weekend working and deploying generators
- Dead-jointing work also employed to accelerate HV connection process with NGED.