Location
Wigan
Developer
Owner-led
Project
Our Client had power demands which were beyond the network capacity for its factory, so was supplementing with generators. They wanted to move forward with their own permanent connection as a way of bringing costs down.
Contract
- Electrical connection
- Onsite substation.
Delivery
- Existing designs proposed crossing third party land, creating landrights challenges
- We redesigned the connection, securing a new route which required 250m of cabling and a substation on our Client’s land.